A Venture Monitoring Physique for the monitoring and supervision of each problem associated to the development of the liquefied pure gasoline receiving and regasification terminal in Vassiliko is beneficial inside the Ministry by the Minister of Vitality Giorgos Papanastasiou after as we speak's resumption of building work on the terminal.
“To strengthen and create belief between the events that there’s correct and acceptable monitoring of the mission, the Minister and his group create a Venture Monitoring Company inside the Ministry, an Company that can have the data and coaching to have the ability to supervise and to observe the mission and on the similar time be capable of work in all instructions with the powers that the Minister will grant him”, stated Mr. Papanastasiou in an announcement to the KYPE, whereas relating to the brand new timetable for the completion of the mission, he stated that this shall be filed by the development firm inside the subsequent week or the week after.
The Minister of Vitality along with the President of the Republic visited as we speak the development website in Vasiliko, the place they got a tour and knowledgeable by the development firm in regards to the progress of the mission implementation.
Relating to the Venture Monitoring Physique, Mr. Papanastasiou defined that it’ll encompass 1-2 engineers who’re in a position to perceive precisely what’s being accomplished and who shall be accountable for monitoring and supervising the mission and shall be in fixed contact with the Ministry, DEFA and ETYFA and the manufacturing firm. They may also handle any disputes that come up. “We is not going to let variations develop and create relationship issues,” defined Mr. Papanastasiou.
“They would be the ones who will monitor all the person points of the mission, whether or not it’s the relations between the businesses or an bill that was left unpaid as a result of there was no approval, all of this shall be monitored by the Company, in order to restrict the paperwork and to not additional delay the mission”, he famous.
“This Company would be the eyes of the Ministry within the mission and in reality within the subject, on the bottom and never within the places of work”, emphasised Mr. Papanastasiou, clarifying that the Company is not going to intervene with the contractual obligations of the 2 contracting events.
In response to a query relating to whether or not there may be now a brand new schedule, the Minister of Vitality said that “the brand new information is that now we have inherited one other two months of delay, so the schedule that was indicated then, though it was practical, as we speak just isn’t potential to satisfy” .
He added that “we’re at the moment awaiting a brand new schedule, which the development firm has promised to submit inside the subsequent week or the week after.”
Commenting that the resumption of labor creates expectations, Mr. Papanastasiou said that “precisely the explanation it creates expectations is as a result of now we have misplaced expectations for the reason that time when folks hear a couple of pure gasoline terminal and see nothing”.
Explaining that the problem of electrical energy may be very excessive on the Authorities's agenda, the Minister of Vitality indicated that this mission wants good administration, and the administration issues either side, each the Chinese language consortium and the aspect of DEFA and ETYFA.
With regard to a potential monetary distinction between the 2 sides, the Minister of Vitality famous that he himself identifies such an object within the matter of the terminal pier. “There isn’t a distinction anyplace else and that's why we're specializing in that one merchandise referred to as the jetty, to see what occurred, what we put within the bids and what's being constructed,” he stated, explaining that if there’s a distinction between what was awarded as a bid with what’s manufactured as a result of it was indicated to the development firm, “then we bear the accountability” but when what’s included within the provide is what’s manufactured then it’s as much as the development firm to resolve it.
KYPE